Skip to main content

syncbuilding

Home β€Ί Resources β€Ί ACT Building Approval Checklist 2025
ACT Building Approvals β€” Updated 2025

ACT Building Approval
Checklist 2025

Everything a Canberra homeowner needs to know before starting a renovation, extension, or new home build. DA vs BA explained, step-by-step process, official forms, real timelines, and what Sync handles for you.

Last updated: January 2025 Β Β·Β  Reflects ACT Planning Act 2023 Β Β·Β  Form AF2025-13
Quick answer: Do you need approval?
Internal cosmetic work(painting, flooring, tiling, fixtures) β†’ Usually no approval needed
Structural changes(wall removal, additions) β†’ Building Approval (BA) required
New extensions, decks, sheds→ May qualify for DA-Exempt BA or need full DA
New home, knockdown rebuild→ Development Application (DA) + BA required
Designated Areas (near lake, ANU etc.)β†’ NCA Works Approval may also apply

Not sure about your specific project?

0452 394 567

Fady answers β€” free, no obligation

⚠️ ACT Planning System changed in 2023 β€” this guide reflects the current rules

The ACT's new Planning Act 2023 came into effect in August 2023, introducing significant changes to development applications, approval pathways, and what qualifies as exempt development. If you're relying on advice from before 2023, some of it may no longer be accurate. This guide reflects the current system as at January 2025.

ACT building approvals are legitimately more complex than most states in Australia. Canberra has a leasehold land system (you don't own the land β€” you hold a 99-year lease), a unique planning authority structure, and suburb-specific heritage controls that don't exist elsewhere. Getting this wrong can set your project back by months.

This guide was written by the Sync Building Projects team to give Canberra homeowners a genuine plain-English explanation of what the ACT approval system requires β€” based on years of managing approvals for renovations, extensions, and new homes across every suburb in the territory.

Section 1

The 4 Types of ACT Approval
β€” and When Each Applies

Understanding which approval pathway applies to your project is the first β€” and most important β€” step. Getting this wrong wastes weeks.

βœ“ Exempt Development

No Approval Needed

Minor works that meet specific rules β€” no application required

0 days β€” start immediately
Internal cosmetic work (painting, new floors, fixtures)
Like-for-like replacement of existing elements
Some minor retaining walls under 1m
Some fences (where compliant with code)
Skylights in certain circumstances
πŸ“‹ DA-Exempt Building Approval

Building Approval Only

No DA needed if all rules in the code are met β€” faster pathway

4–8 weeks typical BA timeframe
Class 10 structures: sheds, garages, carports, pergolas, pools, studios (non-habitable)
Must comply exactly with Single Residential Dwelling Code or Schedule 1 of Planning Code
ALL rules must be met β€” one breach triggers DA requirement
"1N Exempt Declaration" if almost compliant (1–2 minor rule breaches)
Certifier engaged directly β€” no ACTPLA application needed
πŸ“ Development Application + BA

Full DA Required

Most extensions, new homes, knockdown rebuilds, and significant structural work

8–20 weeks for DA + BA combined
Any new habitable space added to a dwelling
Second storey additions
New dwelling / knockdown rebuild
Granny flat / secondary dwelling
Works that don't meet DA-exempt criteria
Heritage-affected properties
πŸ›οΈ NCA Works Approval

National Capital Authority

Applies in Designated Areas β€” in addition to ACT Planning requirements

Additional 4–12 weeks on top of DA/BA
Designated Areas include: Parliamentary Zone, Lake Burley Griffin foreshores, ANU campus, major approach routes
Required for ALL works in Designated Areas β€” no exemptions
Applies to construction, alteration, landscaping, tree removal, excavation
Check with NCA first at nca.gov.au
NCA fees are separate from ACT Planning fees
πŸ’‘ The key question: Is your project "habitable" or "non-habitable"?

In ACT planning, this distinction matters enormously. Non-habitable structures (sheds, garages, pergolas, pools) can often use the faster DA-Exempt pathway. Habitable spaces (anything people sleep, live, or work in) almost always require a full DA. If you're unsure, ask Sync β€” we confirm this in the free feasibility consultation before any money changes hands.

Section 2

Do I Need Approval? β€”
Quick Reference by Project Type

Use this as a starting guide. Every block is different β€” setbacks, easements, heritage overlays, and block coverage all affect what's required. Confirm with your builder or the ACT Planning portal.

ACT Building Approval β€” Common Residential Works Guide (2025)
Work Type DA Required? BA Required? Notes
Internal painting, new flooring, tilingNoNoPurely cosmetic work with no structural changes
Kitchen renovation (no structural changes)NoNo**Electrical and plumbing still require licensed trades. If walls are moved, BA required.
Bathroom renovation (no structural changes)NoNo**Licensed plumber & waterproofer required. If layout changes affecting structure, BA needed.
Internal wall removal (non-load-bearing)SometimesYesBA required. If wall is load-bearing, structural engineering and BA both required.
Internal wall removal (load-bearing)SometimesYesStructural beam and engineering certificate required. BA mandatory.
Garage / carport (Class 10)Maybe*Yes*DA-Exempt BA if all code rules met. Full DA if rules breached.
Shed / workshop (Class 10, non-habitable)Maybe*Yes*Often DA-Exempt if within size limits and setbacks. Check code rules carefully.
Pergola / covered outdoor area (unenclosed)Maybe*Yes*May be DA-Exempt if compliant. Enclosed or roofed patios more likely to need DA.
Swimming pool / spaMaybe*Yes*DA-Exempt BA may apply if within setbacks. Pool fencing is a mandatory BA requirement.
Ground floor extension (adding habitable space)UsuallyYesDA required for any habitable addition. Setbacks, block coverage, and height all assessed.
Alfresco addition (covered, attached)OftenYesDepends on size and whether it's enclosed. Open structures may qualify for DA-Exempt BA.
Second storey additionYesYesAlways requires DA. Height controls, shadow impact, and overlooking assessed by ACT Planning.
New dwelling / custom home buildYesYesFull DA mandatory. Energy report, soil assessment, structural engineering also required.
Knockdown rebuildYesYesDemolition approval + DA + BA all required. Asbestos assessment mandatory for pre-1990 homes.
Granny flat / secondary dwellingYesYesDA required. Must meet ACT secondary dwelling criteria including minimum block size.
Heritage-listed property β€” any external workYesYesHeritage requirements add additional assessment. Demolition of heritage homes typically prohibited.

⚠️ This table is a guide only. Your specific block’s zone, setbacks, existing coverage, easements, and any heritage overlay all affect what’s required. Book a free feasibility assessment with Fady for your specific project.

Section 3

DA-Exempt Building Approval
β€” The Faster Pathway Explained

This is the most misunderstood aspect of ACT building approvals β€” and the one that can save you the most time and money if you qualify.

Three approval pathways for Class 10 structures

Class 10 = non-habitable structures: sheds, garages, carports, pergolas, pools, studios, decks

βœ“ Fastest

DA-Exempt Building Approval

Skip the DA entirely. Engage a private certifier directly for your Building Approval.

Must comply 100% with Single Residential Dwelling Code OR Schedule 1 of Planning Code
All setback, height, and coverage rules must be met exactly
Any single rule breach disqualifies you from this pathway
Certifier checks compliance and issues BA
⏱ 4–8 weeks Β· No DA fee
~ Middle Ground

1N Exempt Declaration

For structures that almost qualify β€” where only 1 or 2 minor rules are breached.

Applies when structure is largely compliant but has minor rule deviations
Certifier assesses whether the breach is minor enough to qualify
Not all certifiers offer this pathway β€” confirm with Sync or your certifier
Still avoids full DA β€” significant time saving
⏱ 6–10 weeks Β· Reduced fees
βœ— Slowest

Full Development Application

Required when the project doesn't meet DA-exempt criteria or involves habitable space.

Lodged with ACT Planning Authority
Public notification period (2 weeks for most residential DAs)
Assessment against Territory Plan provisions
Additional reports may be required (heritage, traffic, trees)
Certifier still engaged for BA after DA approved
⏱ 10–20 weeks Β· Full fees apply
βœ“ Builder's tip: Get a pre-DA feasibility check before you commit to design fees

Before spending $5,000–$15,000 on architectural drawings, confirm which approval pathway applies to your specific project. Sync does this assessment free as part of the initial consultation β€” it takes 20 minutes on site and can save months of redesign if the project doesn't qualify for the pathway you assumed. Architects who don't regularly work in the ACT sometimes produce drawings for projects that don't qualify for DA-Exempt BA β€” costing clients a full DA process they didn't anticipate.

Section 4 β€” The Main Checklist

ACT Building Approval Checklist
β€” Step by Step

Follow these steps in order. Skipping or reversing steps is the most common cause of delays on Canberra renovation and building projects.

πŸ”

Phase A β€” Before You Apply for Anything

Feasibility, site assessment, and confirming your approval pathway

1–2 weeks Β· Do this before engaging any designer
1

Confirm your block's planning zone and constraints

Look up your property on the ACT Planning Portal (planning.act.gov.au) to identify your planning zone (RZ1, RZ2, CFZ, etc.), any heritage overlays, tree protection orders, easements, and existing development approvals on the block. Each of these can affect what's permissible β€” and some constraints aren't visible from street level.

Key things to check: setback requirements from boundaries (front, side, rear), maximum block coverage percentage, height limits, and whether the property is in a heritage precinct.

You or Sync 1–3 days ACT Planning Portal
ACT Planning Portal
2

Check if a DA, DA-Exempt BA, or no approval is needed

Use the guide in Section 2 above and the ACT Planning Portal's exemption checker to determine your approval pathway. For any project that could qualify for DA-Exempt BA β€” confirm this before starting design, as it significantly affects your timeline and costs.

For pre-1990 homes: arrange an asbestos assessment at this stage β€” required before demolition or major structural work regardless of approval pathway.

You or Sync 1–2 days ⚠️ Pre-1990 homes need asbestos assessment
3

Check for NCA Works Approval requirement

If your property is in or adjacent to a Designated Area (Lake Burley Griffin foreshores, Parliamentary Zone, ANU area, Anzac Parade corridor, major approach routes), you may need a Works Approval from the National Capital Authority (NCA) in addition to ACT Planning approvals. There are no exemptions from this requirement. Check at nca.gov.au.

You or Sync 1 day NCA Works Approval Portal
NCA Works Approval info
4

Engage a licensed builder and/or designer early

For complex projects, involve a builder in the design stage β€” before you've committed to drawings. A builder who knows ACT approval requirements (like Sync) can identify compliance issues early, preventing costly redesigns. The best outcome is achieved when architect, designer, and builder are aligned from the beginning β€” not when the builder is brought in after DA-lodgement drawings are complete.

You Varies
πŸ“

Phase B β€” Development Application (if required)

Skip this phase if your project qualifies for DA-Exempt Building Approval

4–10 weeks from lodgement to decision (typical residential DA)
5

Prepare DA documentation and drawings

A DA requires: site plan showing block dimensions and setbacks, floor plans showing proposed works, elevations showing height and external appearance, a Statement of Environmental Effects (SEE), and sometimes additional reports (tree assessment, heritage impact, traffic impact, stormwater management). The level of documentation required increases with project complexity.

Since the new Planning Act 2023, DAs must also demonstrate how the proposal meets the Territory Plan's relevant design principles β€” not just technical compliance with measurements.

Architect or Designer 4–12 weeks $5,000–$20,000 typical design fees
6

Lodge the Development Application

DAs are lodged through the ACT Planning Portal. The application must include all required documents, the development application form, and payment of the DA fee (based on construction cost estimate using the Building Cost Determination). Incomplete applications are rejected without refund of the lodgement fee.

ACT Planning Authority has a dedicated hotline for new system questions: 02 6205 0580. Email: [email protected]

Owner, Architect, or Sync ACT Planning Portal DA fee: based on construction cost
DA lodgement portal
7

Public notification period

Most residential DAs are publicly notified for 15 business days. Neighbours can make representations (objections or support). If objections are received, the assessment process may take longer. Heritage applications and significant developments have extended notification requirements under the Planning Act 2023.

ACT Planning Authority 15 business days minimum
8

DA decision β€” notice of decision issued

ACT Planning Authority issues a notice of decision either approving (with or without conditions) or refusing the DA. If approved, note any conditions carefully β€” some conditions must be met before construction commences. Conditions can include design modifications, landscape works, or further reports. Your DA approval has a time limit β€” commencement of construction must begin within the approval period or a new application is required.

ACT Planning Authority Typically 20–45 business days from lodgement
πŸ—οΈ

Phase C β€” Building Approval (BA)

Required for all construction β€” whether DA-Exempt or with a full DA

3–6 weeks typical BA timeframe
9

Engage a licensed building certifier

A certifier is a licensed professional who reviews your construction drawings against the National Construction Code (NCC) and issues the Building Approval. They also carry out mandatory inspections at key build stages. You can use a private certifier (faster) or the ACT Government's own certification service. Sync has established relationships with Canberra certifiers and coordinates this on your behalf.

Certifier must be engaged before the BA application is submitted. The certifier's appointment is registered with Access Canberra using the current approved form (Form AF2025-13, approved August 2025).

Owner or Builder (Sync) Form AF2025-13 Certifier fees: $1,500–$6,000+ depending on project
BA forms β€” ACT Planning
10

Submit Building Approval application with construction drawings

The BA application requires: detailed construction drawings (structural, architectural, services), a structural engineer's report (stamped plans), energy efficiency report (NCC 7-star for new homes from 2023), soil assessment, and the cost of works estimate. All plans must comply with the NCC and relevant ACT standards. Incomplete or non-compliant drawings are a major cause of BA delays.

Architect + Engineer + Certifier 2–4 weeks to prepare
11

Building Approval issued β€” with mandatory inspection stages

When the BA is issued, it will specify the mandatory inspection stages. For most residential construction, these include: footings/slab before pour, frame inspection before lining, and pre-completion/final inspection. Missing a mandatory inspection can void the BA β€” Sync schedules all inspections as part of the build programme.

Certifier 3–6 weeks from submission
12

Apply for Commencement Notice before construction starts

Before any construction commences, your licensed builder must apply for a Commencement Notice. This registers the builder with ACT Planning and confirms the build start date. The certifier issues the Commencement Notice after the BA is in place. You cannot legally start construction without this β€” doing so is a building offence under the Building Act 2004.

Builder (Sync) Commencement Notice form ⚠️ Do not commence without this
Commencement Notice form
πŸ”¨

Phase D β€” During Construction

Compliance obligations during the build

Duration of construction
13

Mandatory stage inspections at specified points

The certifier must carry out inspections at the mandatory stages specified in the BA. These typically include footing/slab inspection (before concrete is poured), frame inspection (before wall linings go on), waterproofing inspection (before tiling in wet areas), and a final inspection before the Certificate of Occupancy is issued. These cannot be skipped or combined β€” each must be completed and signed off before the next stage begins.

Certifier + Builder ⚠️ Cannot be skipped
14

Notify certifier of any variations to approved plans

If anything changes from the approved BA drawings during construction β€” even minor changes β€” the certifier must be notified. Some variations require a BA amendment before work can proceed. Building outside the approved plans is a building offence and can invalidate the Certificate of Occupancy. Sync manages all variation notifications as part of on-site management.

Builder (Sync) ⚠️ Variations must be approved before proceeding
βœ…

Phase E β€” Completion & Handover

Final approvals, certificates, and documentation

1–3 weeks at project completion
15

Final inspection and Certificate of Occupancy issued

After the final mandatory inspection is passed, the certifier issues an Occupancy Certificate (OC). This is the legal confirmation that the building work complies with the BA and is approved for occupation. No one can legally occupy a new dwelling without an Occupancy Certificate. For renovations and extensions, an OC is also required and must be obtained before handover.

Since 2025, there is a requirement to nominate the type of Certificate of Occupancy at the Building Approval application stage (Section 26(2)(b) of the Building Act 2004). Sync handles this nomination.

Certifier 1–5 days after final inspection
16

Obtain all certificates and documentation at handover

At handover, ensure you receive: the Occupancy Certificate, the Building Approval with all stage inspection certificates, structural engineer's certificate, energy compliance certificate, waterproofing certificate (for bathrooms), all trade compliance certificates (electrical Certificate of Compliance, plumbing compliance certificate), warranties and manuals, and the builder's statutory warranty documentation. Sync provides all of this as standard at every project handover.

Builder (Sync) + Certifier ⚠️ Keep all documents permanently β€” needed when you sell

Want Sync to handle the entire approvals process?

Every Sync project includes full management of the DA, BA, certifier engagement, stage inspections, and Occupancy Certificate β€” you don't navigate any of this yourself.

Book a Free Consultation

Section 6

Realistic ACT Approval Timelines

These are realistic timeframes from the Sync team's experience managing approvals across Canberra β€” not the theoretical minimums listed in government documentation.

ACT Approval Timelines β€” Realistic Estimates (2025)
Pathway Best Case Typical If Delays
No approval needed (cosmetic work) Immediate Start day 1 N/A
DA-Exempt Building Approval 3 weeks 4–6 weeks 8–10 weeks (if drawings need revision)
Full DA (straightforward residential) 8 weeks 12–16 weeks 20+ weeks (objections, conditions, revisions)
Full DA (complex / heritage / significant) 14 weeks 20–28 weeks 30–52+ weeks (appeals, referrals)
Building Approval (after DA or DA-exempt) 2 weeks 3–5 weeks 6–8 weeks (incomplete plans)
NCA Works Approval (Designated Areas) 4 weeks 6–10 weeks 12–20 weeks (heritage, heritage items)

⚠️ These timelines run concurrently with design preparation time β€” the full pre-construction period (design + approvals) is typically 3–9 months for projects requiring a DA. This is why Sync recommends getting in touch 6–9 months before your preferred build start date.

Section 7

ACT Building Approval Fees
& Costs β€” What to Budget

Approval costs are additional to construction costs and are often underestimated. Budget for these upfront β€” they're non-negotiable and cannot be recovered.

DA Lodgement Fee

$500–$2,500+

Based on the estimated cost of works using the ACT Building Cost Determination. Calculated by ACT Planning at lodgement. Non-refundable if the DA is refused.

Private Certifier Fees

$1,500–$6,000+

Covers BA assessment, stage inspections, and Occupancy Certificate. Varies by project size and complexity. Set by the certifier independently of government fees.

Architect / Designer Fees

$5,000–$20,000+

Preparation of DA and BA drawings. Scales with project complexity. For major extensions and new homes, architectural fees can be 5–10% of construction cost.

Structural Engineer

$1,500–$8,000+

Required for all structural changes β€” wall removals, extensions, new homes. Provides stamped structural drawings submitted with the BA application.

Energy Efficiency Report

$500–$1,500

NatHERS assessment required for new homes and significant additions under NCC 2022 (7-star energy rating). Prepared by an accredited energy assessor.

NCA Works Approval Fee

$400–$5,000+

Applies only to Designated Areas. Calculated by the NCA based on the estimated cost of works. In addition to all ACT Planning fees.

πŸ“Œ Total pre-construction cost guide for typical projects
Ground floor extension (DA required): $8,000–$25,000 in total approval and professional fees
Second storey addition: $12,000–$35,000 in approval and professional fees
New custom home (full DA + BA): $18,000–$55,000 in professional and approval fees
Knockdown rebuild: $22,000–$60,000+ including demolition permits, asbestos, and all approvals

Section 8

Official ACT Building Approval
Forms & Resources

All current official forms β€” updated links as at January 2025. Bookmark these rather than searching each time β€” the ACT government restructures its websites periodically.

πŸ“‹

Appointment of Certifier & Application for Building Approval Form AF2025-13

The primary BA application form. Approved August 2025 β€” replaces AF2016-85. Completed by the owner. Required before any BA process can begin. Note the new requirement to nominate Certificate of Occupancy type at this stage (Section 26(2)(b), Building Act 2004).

Download from ACT Planning
πŸ“‹

Appointment of Builder & Application for Commencement Notice

Registers your licensed builder and sets the official start date for construction. Must be lodged with Access Canberra before any work begins. Your builder cannot legally start without this being in place.

Download from ACT Planning
πŸ“‹

Building Commencement Notice

Separate from the Application for Commencement Notice β€” this is the confirmation form lodged once approvals are in place and a firm construction start date is confirmed. Keeps ACT Planning and Access Canberra informed of build progress.

Download from ACT Planning
🌐

ACT Planning Portal β€” DA Lodgement & Property Search

Use this to lodge a DA, search your property for planning zone and constraints, check DA-exempt eligibility, and access the Territory Plan. The portal was updated significantly with the Planning Act 2023 transition.

ACT Planning Portal
πŸ“–

National Construction Code (NCC 2022)

The code that all building work in Australia must comply with. For ACT residential construction, Volume 2 (Class 1 and 10 buildings) applies. The 2022 edition introduced the 7-star energy efficiency requirement. New edition expected 2025 β€” check ABCB for updates.

Access NCC at ABCB
πŸ›οΈ

NCA Works Approval β€” Designated Areas

For any construction, alteration, or demolition within a Designated Area. No exemptions apply under the PALM Act. Check whether your property is in a Designated Area at the NCA website before starting any approval process.

NCA Works Approval info
πŸ’°

Building Cost Determination β€” Fee Calculator

Used to calculate your DA lodgement fee and certifier fees based on construction cost. Published by the ACT Government's Environment, Planning and Sustainable Development Directorate on the ACT Legislation Register.

ACT Legislation Register
☎️

ACT Planning β€” New System Hotline

For questions about the new Planning Act 2023 system. Phone: 02 6205 0580. Email: [email protected]. The Land Planning and Building Services shopfront at 8 Darling St, Mitchell is closed for renovations until January 2026 β€” use phone and email.

Section 10

ACT Building Approval
FAQ β€” 10 Questions Answered

The most common ACT approval questions Fady gets asked before and during project consultations.

Let Sync Handle the Approvals

Every Sync project includes full approvals management β€” DA, BA, certifier, stage inspections, and Occupancy Certificate. You don't navigate any of this yourself.

Book a Free Consultation

Prefer to talk to a builder directly?

0452 394 567

Fady answers β€” no reception, no delays.

Do I need a Development Application for a kitchen renovation?

Generally no β€” a kitchen renovation that doesn't involve structural changes (no wall removal, no changes to the building's exterior or footprint) doesn't require a DA or BA. However, the work must be carried out by licensed trades: a licensed electrician for any electrical work, a licensed plumber for plumbing changes, and a licensed waterproofer if waterproofing is involved. If you're removing a wall as part of the renovation, a BA is required β€” and if that wall is load-bearing, structural engineering is also needed.

Straightforward residential DAs (ground floor extensions, second storey additions that meet standard setbacks) typically take 12–16 weeks from lodgement to decision. Complex DAs involving heritage precincts, significant developments, or multiple referrals can take 20–28 weeks or longer. The 15-business-day public notification period is included in this. The ACT Government's stated target for residential DAs is 20 business days, but this is rarely achieved in practice.

No. It is illegal to commence any development that requires a DA without first obtaining DA approval and a subsequent Building Approval and Commencement Notice. Commencing work without approval is a building offence under the Building Act 2004 and the Planning Act 2023. The penalty includes potential demolition orders requiring you to remove the unapproved work at your own cost. Sync never commences work without all required approvals in place.

A Development Application (DA) is a planning approval β€” it assesses whether your proposed development is appropriate for the location, zone, and neighbourhood context. It looks at setbacks, height, appearance, and impact on neighbours. A Building Approval (BA) is a technical construction approval β€” it assesses whether your construction drawings comply with the National Construction Code (structural, fire safety, energy efficiency, waterproofing). Most projects requiring a DA also need a BA. Some projects only need a BA (DA-Exempt pathway). Both must be obtained before construction can legally start.

Removing a non-structural internal wall generally requires a Building Approval but not a DA. Removing a load-bearing wall always requires a Building Approval and a structural engineer's report showing the beam specification. In heritage-listed properties or heritage precincts, even internal wall removal may require a DA assessment. Sync confirms the requirement for your specific property and wall type during the feasibility consultation.

This is a faster approval pathway for non-habitable structures (Class 10 buildings β€” sheds, garages, carports, pergolas, pools, studios) that comply exactly with all rules in the Single Residential Dwelling Code or Schedule 1 of the Planning Code. If your structure meets ALL the rules (setbacks, height, size, coverage), you can skip the DA entirely and go directly to a Building Approval with a private certifier β€” saving 4–8 weeks and the DA fee. One rule breach disqualifies you from this pathway. There's also a "1N Exempt Declaration" for structures that are almost compliant with only 1–2 minor rule breaches.

In Canberra, all land is held under a 99-year Crown Lease β€” you don't own the land freehold, you hold a lease. Your Crown Lease specifies the permitted uses for your block (residential, commercial, etc.) and any specific conditions. Any development must be consistent with Crown Lease conditions. In most standard residential cases, the lease conditions align with the Territory Plan and don't add extra restrictions β€” but for unusual projects or commercial conversions, the lease must be checked. Sync checks lease conditions for relevant projects as part of the feasibility stage.

Yes β€” a Building Approval is required. A DA may or may not be required depending on whether your shed/garage qualifies for the DA-Exempt pathway. To qualify for DA-Exempt BA: it must be non-habitable (Class 10), it must be within the setbacks specified in the code, it must not exceed the size and height limits, and your total block coverage must not be exceeded. If all conditions are met, you can engage a certifier directly without lodging a DA. If any condition is breached, a full DA is required before the BA can be obtained.

Yes β€” a Building Approval is required. A DA may or may not be required depending on whether your shed/garage qualifies for the DA-Exempt pathway. To qualify for DA-Exempt BA: it must be non-habitable (Class 10), it must be within the setbacks specified in the code, it must not exceed the size and height limits, and your total block coverage must not be exceeded. If all conditions are met, you can engage a certifier directly without lodging a DA. If any condition is breached, a full DA is required before the BA can be obtained.

Skip the Paperwork β€” Talk to the Builder

Book a Free ACT Approval
Consultation with Fady

On the call, Fady will confirm which approvals apply to your project, give you a realistic timeline, and outline what Sync will handle on your behalf. Free, no obligation, no sales pitch β€” just straight answers from the builder.

βœ“ Free approval pathway assessment for your project
βœ“ Realistic timeline and cost estimate for approvals
βœ“ Sync handles all approvals on your behalf
βœ“ Response within 24 hours

Prefer to call now?

0452 394 567

Fady answers β€” no call centre, no reception.

    We respond to all enquiries within 24 hours. Your details are kept private.

    πŸ“ž Call Fady Free Consultation