The ACT's new Planning Act 2023 came into effect in August 2023, introducing significant changes to development applications, approval pathways, and what qualifies as exempt development. If you're relying on advice from before 2023, some of it may no longer be accurate. This guide reflects the current system as at January 2025.
ACT building approvals are legitimately more complex than most states in Australia. Canberra has a leasehold land system (you don't own the land β you hold a 99-year lease), a unique planning authority structure, and suburb-specific heritage controls that don't exist elsewhere. Getting this wrong can set your project back by months.
This guide was written by the Sync Building Projects team to give Canberra homeowners a genuine plain-English explanation of what the ACT approval system requires β based on years of managing approvals for renovations, extensions, and new homes across every suburb in the territory.
Section 1
Understanding which approval pathway applies to your project is the first β and most important β step. Getting this wrong wastes weeks.
In ACT planning, this distinction matters enormously. Non-habitable structures (sheds, garages, pergolas, pools) can often use the faster DA-Exempt pathway. Habitable spaces (anything people sleep, live, or work in) almost always require a full DA. If you're unsure, ask Sync β we confirm this in the free feasibility consultation before any money changes hands.
Section 2
Use this as a starting guide. Every block is different β setbacks, easements, heritage overlays, and block coverage all affect what's required. Confirm with your builder or the ACT Planning portal.
Section 3
This is the most misunderstood aspect of ACT building approvals β and the one that can save you the most time and money if you qualify.
Class 10 = non-habitable structures: sheds, garages, carports, pergolas, pools, studios, decks
Before spending $5,000β$15,000 on architectural drawings, confirm which approval pathway applies to your specific project. Sync does this assessment free as part of the initial consultation β it takes 20 minutes on site and can save months of redesign if the project doesn't qualify for the pathway you assumed. Architects who don't regularly work in the ACT sometimes produce drawings for projects that don't qualify for DA-Exempt BA β costing clients a full DA process they didn't anticipate.
Section 4 β The Main Checklist
Follow these steps in order. Skipping or reversing steps is the most common cause of delays on Canberra renovation and building projects.
Feasibility, site assessment, and confirming your approval pathway
1β2 weeks Β· Do this before engaging any designerSkip this phase if your project qualifies for DA-Exempt Building Approval
4β10 weeks from lodgement to decision (typical residential DA)Required for all construction β whether DA-Exempt or with a full DA
3β6 weeks typical BA timeframeCompliance obligations during the build
Duration of constructionFinal approvals, certificates, and documentation
1β3 weeks at project completionEvery Sync project includes full management of the DA, BA, certifier engagement, stage inspections, and Occupancy Certificate β you don't navigate any of this yourself.
Section 6
These are realistic timeframes from the Sync team's experience managing approvals across Canberra β not the theoretical minimums listed in government documentation.
β οΈ These timelines run concurrently with design preparation time β the full pre-construction period (design + approvals) is typically 3β9 months for projects requiring a DA. This is why Sync recommends getting in touch 6β9 months before your preferred build start date.
Section 7
Approval costs are additional to construction costs and are often underestimated. Budget for these upfront β they're non-negotiable and cannot be recovered.
Section 8
All current official forms β updated links as at January 2025. Bookmark these rather than searching each time β the ACT government restructures its websites periodically.
The primary BA application form. Approved August 2025 β replaces AF2016-85. Completed by the owner. Required before any BA process can begin. Note the new requirement to nominate Certificate of Occupancy type at this stage (Section 26(2)(b), Building Act 2004).
Download from ACT PlanningRegisters your licensed builder and sets the official start date for construction. Must be lodged with Access Canberra before any work begins. Your builder cannot legally start without this being in place.
Download from ACT PlanningSeparate from the Application for Commencement Notice β this is the confirmation form lodged once approvals are in place and a firm construction start date is confirmed. Keeps ACT Planning and Access Canberra informed of build progress.
Download from ACT PlanningUse this to lodge a DA, search your property for planning zone and constraints, check DA-exempt eligibility, and access the Territory Plan. The portal was updated significantly with the Planning Act 2023 transition.
ACT Planning PortalThe code that all building work in Australia must comply with. For ACT residential construction, Volume 2 (Class 1 and 10 buildings) applies. The 2022 edition introduced the 7-star energy efficiency requirement. New edition expected 2025 β check ABCB for updates.
Access NCC at ABCBFor any construction, alteration, or demolition within a Designated Area. No exemptions apply under the PALM Act. Check whether your property is in a Designated Area at the NCA website before starting any approval process.
NCA Works Approval infoUsed to calculate your DA lodgement fee and certifier fees based on construction cost. Published by the ACT Government's Environment, Planning and Sustainable Development Directorate on the ACT Legislation Register.
ACT Legislation RegisterRelated Pages